TO: BOARD OF TRUSTEES

ITEM NO:

FROM: PRESIDENT

 

SUBJECT: Restroom Improvements (Shuhaw Hall, Barnett Hall, Bailey Hall Plumbing Upgrades) Scheduled Maintenance Projects, Ratification And Award of Bid

DATE
4-10-01

REASON FOR BOARD CONSIDERATION

CONSENT

ENCLOSURES

1 of 1

BACKGROUND

This project will provide plumbing repair and cosmetic upgrades. Pre-bid cost estimate was $450,000.00.

Bids were to be opened on March 12th with the following results:

BIDDER

LOCATION

BID

1. Carr's Construction

Windsor

$189,450.00

2. C.G. Builders, Inc.

Santa Rosa

$228,416.00

3. J.T & T Enterprises dba James E. Thompson

Windsor

$257,500.00

4. Page Construction Co.

Novato

$274,672.00

5. J.K. Merz Construction

San Rafael

$325,000.00

6. J.M.A. Construction

San Francisco

$348,000.00

7. R. J. Construction Co.

Santa Rosa

$397,766.00

BUDGET IMPACT

$94,725.00 Capital Projects Fund 41 (50%)

$94,725.00 State Scheduled Maintenance

 

ADMINISTRATIVE RECOMMENDATION

It is recommended that the Board of Trustees award the low bid in the amount of $189,450.00 to Carr's Construction Service, of Windsor for the Restroom Improvements (Shuhaw Hall, Barnett Hall, Bailey Hall Plumbing Upgrades) Scheduled Maintenance Project.