Change Order #9, the final change order for this project, consists of a number of "back check" items (under continued review by DSA, the architect and the college) which reflect either changes to the original design to account for actual conditions impacted by equipment installations and/or increased stringency in code interpretation.
Item #1: Grade coordination & rework at existing inlet box required to coordinate grades
btween the Increment I and II construction projects $ 1,775.00
Item # 2: Installation of GFI electrical receptacles in Room 118 per electrical engineer
rquirements $ 2,768.00
Item #3: Revise window frame at Health Services to increase stiffness and safety of
installed windows $ 3,428.00
Services corridor. $3,428.00
6. Additional control points for the Energy Management Control $9,225.00
Panels and installation of HVAC points and valve systems ________
.
The total of Change orders 1-9 is $37,238.00 for a net increase to the original contract of $37,238.00.
BUDGET IMPACT
($82,552.00) Capital Construction (Fund 41) Reduction
ADMINISTRATIVE RECOMMENDATION
That the Board of Trustees approve the William B. Race Health Sciences Building Change Order #9 in the credit amount of $82,552.00) for a revised contract amount of $7,182,738.00.