TO: BOARD OF TRUSTEES

ITEM NO.

FROM: PRESIDENT

 

SUBJECT: William B. Race Health Sciences Building Construction Project, Change Order #9

DATE
2-8-00

REASON FOR BOARD CONSIDERATION

ACTION

ENCLOSURES

1

BACKGROUND

At this writing, Change Order #9 is under discussion with the general contractor, the architect and the project inspectors. The intent is to have Change Order #9 become the final wrap up item for the project. The intent is to have it include all remaining additive and deductive items which would then close out the project. If concluded jprior to the February 1st Board Facilities Committee. Change Order #9 will be reviewed by the BFC prior to its submission to the Board of Trustees on February 8th. If not, then this item will be carried over until the March Board of Trustees meeting.

BUDGET IMPACT

Forthcoming

 

 

ADMINISTRATIVE RECOMMENDATION