TO: BOARD OF TRUSTEES |
ITEM NO. |
|
FROM: PRESIDENT |
|
SUBJECT: Quinn Swim Center HVAC Scheduled Maintenance Project, Change Order #1 |
DATE |
|
REASON FOR BOARD CONSIDERATION CONSENT |
ENCLOSURES 1 of 1 |
BACKGROUND
Change Order #1 deducts $27,900.00 from the Quinn Swim Center HVAC Scheduled Maintenance Project by changing two (2) HVAC units from steel frame construction to unibody resulting in a lighter yet equally durable and less expensive unit. It also provides for necessary changes to the HVAC system control sensors and modifies the original ductwork. -($27,900.00)
Change Order #1 reduces the contract amount by ten and one tenth percent (10.1%) for a revised contract of $244,525.00.
BUDGET IMPACT
$(13,950.00) Capital Projects Fund 41 (50%)
$(13,950.00) State of California Scheduled Maintenance Funds (50%)
ADMINISTRATIVE RECOMMENDATION
It is recommended that the Board of Trustees approve deductive Change Order #1, in the amount of $27,900.00, for the Quinn Swim Center HVAC Scheduled Maintenance Project, for a revised contract price of $244,525.00.