TO: BOARD OF TRUSTEES

ITEM NO.

FROM: PRESIDENT

 

SUBJECT: Quinn Swim Center HVAC Scheduled Maintenance Project, Change Order #1

DATE
5-8-01

REASON FOR BOARD CONSIDERATION

CONSENT

ENCLOSURES

1 of 1

BACKGROUND

Change Order #1 deducts $27,900.00 from the Quinn Swim Center HVAC Scheduled Maintenance Project by changing two (2) HVAC units from steel frame construction to unibody resulting in a lighter yet equally durable and less expensive unit. It also provides for necessary changes to the HVAC system control sensors and modifies the original ductwork. -($27,900.00)

Change Order #1 reduces the contract amount by ten and one tenth percent (10.1%) for a revised contract of $244,525.00.

 

 

 

 

 

 

BUDGET IMPACT

$(13,950.00) Capital Projects Fund 41 (50%)

$(13,950.00) State of California Scheduled Maintenance Funds (50%)

 

 

 

 

 

 

ADMINISTRATIVE RECOMMENDATION

It is recommended that the Board of Trustees approve deductive Change Order #1, in the amount of $27,900.00, for the Quinn Swim Center HVAC Scheduled Maintenance Project, for a revised contract price of $244,525.00.