TO: BOARD OF TRUSTEES |
ITEM NO. |
|
FROM: PRESIDENT |
|
SUBJECT: Quinn Pool Repairs Scheduled Maintenance Project, Award of Bid |
DATE |
|
REASON FOR BOARD CONSIDERATION CONSENT |
ENCLOSURES 1 of 1 |
BACKGROUND
This project will re-plaster both pools, replace tile, repair gutter systems and repair the concrete decking. A scheduled maintenance project, the State of California will fund fifty percent (50%) of the $210,000 estimated budget.
Bids were opened on February 17th and there were two responsive bids received. There was a base cost for the re-plastering and a dollar per square foot cost for the concrete repairs to the outer decking.
FIRM BASE BID ALTERNATE A
South Coast Pool, Lakeside, CA $204,000.00 $30 per square foot
Pool Scene, Novato, CA $222,570.00 $18 per square foot
BUDGET IMPACT
$102,000.00 Capital Projects Fund
$102,000.00 State of California Scheduled Maintenance
ADMINISTRATIVE RECOMMENDATION
It is recommended that the Board of Trustees award the low bid in the amount of $204,000.00, to South Coast Pool, of Lakeside, Ca, for the Quinn Pool Repairs Scheduled Maintenance Project.