SUBJECT: Lighting Retrofit Project, Change Order #1

DATE
3-14-00

REASON FOR BOARD CONSIDERATION

CONSENT

ENCLOSURES

1 of 1

BACKGROUND

Change Order #1, the final change order for this project, consists of items necessary to the completion of the project.

The total of Change Order #1 is $21,598.43 for an increase to the original contract amount of $504,512.00 for a revised contract amount of $526,110.43. Change Order #1 represents a net percentage increase to the contract of 4.28%

 

 

 

 

 

 

 

 

 

 

 

 

 

BUDGET IMPACT

$21,598.43 Business Services Budget

 

 

 

ADMINISTRATIVE RECOMMENDATION

It is recommended that the Board of Trustees approve Change Order #1, in the amount of $21,598.43, for the Lighting Retrofit Project, for a revised contract price of $526,110.43.