BACKGROUND
Change Order #15 addresses a series of construction related issues. The seventeen (17) items include:
|
Item 15.1 Replace underground irrigation control wiring |
$ 375.00 |
|
Item 15.2 Add air compressor in Firing Range |
$ 4,490.00 |
|
Item 15.3 Required Reclaimed Water Inspection |
$ 574.00 |
|
Item 15.4 Install door stops and pulls on doors in Scenario Village |
$ 843.00 |
Continued
BUDGET IMPACT
State of California $17,900.00
Capital Projects Fund 41 $ 1,988.00
ADMINISTRATIVE RECOMMENDATION
It is recommended that the Board of Trustees approve Change Order #15, in the amount of $19,888.00, for the Public Safety Training Center At Windsor Construction Project, for a revised contract price of $12,147,755.00.
Public Safety Training Center, Change Order #15
Continued
|
Item 15.5 Reimburse SRJC for PG & E costs |
.-$3,743.00 |
|
Item 15.6 Reduction in signage |
-$ 765.00 |
|
Item 15.7 Install protective pipe bollards around firing range exterior |
$2,220.00 |
|
Item 15.8 Add additional electrical wiring not listed in specifications |
$3000.00 |
|
Item 15.9 Modify Gun storage locker to staff needs |
$ 997.00 |
|
Item 15.10 Install dryer duct |
$3,950.00 |
|
Item 15.11 Install simulated ATM machine |
$1,148.00 |
|
Item 15.12 Install a warning light in range for DCU |
$ 941.00 |
|
Item 15.13 Install Redwood header board around PG&E and PacBell vaults |
$ 338.00 |
|
Item 15.14 Add power to electric strikers at Firing Range Doors |
$ 751.00 |
|
Item 15.15 Adjust grade at area behind Scenario Village |
$3,353.00 |
|
Item 15.16 Credit SRJC for inserts at Firing Range |
-$ 500.00 |
|
Item 15.17 Backflow Preventor (Skid Pad) modification |
$1,916.00 |
Change Order #15 is $19,888.00. Combined with previous change orders, the total increase in the contract is $363,755.00 including a credit adjustment in Change Order #13 or three and nine one hundredths percent (3.09%).