TO: BOARD OF TRUSTEES |
ITEM NO. |
|
FROM: PRESIDENT |
|
SUBJECT: Burbank Dyer Project, Notice of Completion |
DATE |
|
REASON FOR BOARD CONSIDERATION CONSENT |
ENCLOSURES 1 of 1 |
BACKGROUND
The Burbank Dyer Project is complete. All contractual matters have been finalized and the project is deemed ready for the filing of the Notice of Completion with the County of Sonoma.
There were no change orders on this project.
The final contract price was $22,537.00
BUDGET IMPACT
None
ADMINISTRATIVE RECOMMENDATION
It is recommended that the Board of Trustees accept the Notice of Completion for the Burbank Dyer Project and authorize staff to file said Notice with the County of Sonoma.