TO: BOARD OF TRUSTEES |
ITEM NO. |
|
FROM: PRESIDENT |
|
SUBJECT: Administration of Justice Classroom/Office Remodel Project, Notice of Completion |
DATE |
|
REASON FOR BOARD CONSIDERATION CONSENT |
ENCLOSURES 1 of 1 |
BACKGROUND
The Administration of Justice Classroom/Office Remodel is now complete. There was one change order in the amount of $4,908.00 which increases the original contract price by six percent (6%). The revised contract was $79,359.00.
BUDGET IMPACT
None
ADMINISTRATIVE RECOMMENDATION
It is recommended that the Board of Trustees approve the Notice of Completion for the Administration of Justice Classroom/Office Remodel Project and direct staff to file said Notice with the County of Sonoma.